Project Updates

IL ROUTE 47 WATERMAIN
 
Project Documents:
Staff Report
Pre Construction Notice
Watermain Realignment Exhibit
Route 47 Lane Closure Areas
Eastbound Mill Street Road Closure Exhibit

Project Updates 12/15/2022:

This week the contractor completed the concrete pavement patching on both sides of IL Route 47 & Mill Street.  The removal of the old fire hydrants along the east side of IL Route 47 was also performed.  Removal and replacement of sidewalk required to install the new water services along the east side of IL Route 47 and along the south side of Main Street west of IL Route 47 is anticipated to be completed on Friday.  The removal of the concrete barrier wall and re-striping of the pavement markings on both the east and west sides of Mill Street were completed.  The west side of Mill Street is anticipated to re-opened to traffic at the end of the day Thursday.

Next week, weather dependent, work will continue to place topsoil, seed and blanket along the east and west side of IL Route 47 between Main and Mill Streets.  It is anticipated by mid-next week the project’s traffic control and protection and northbound IL Route 47 lane closure at Mill Street will be removed.

Thank you for your understanding and cooperation as we work to maintain the Village of Huntley infrastructure. If you have any further questions or concerns, please contact the Public Works & Engineering Department at 847-515-5222.